Skip to main content

UK Nuclear- on to 50GW?

A UK Nuclear role– and on to 50GW? 

 In its new report, ‘Nuclear for net Zero’, the Energy System Catapult (ESC) claims that ‘nuclear is potentially an important part of the future Net Zero energy system in the UK’, and although it warns that ‘nuclear cost reduction is a necessary pre-requisite’, it seems confident that costs can be cut. It says ‘Nuclear power plant construction projects do not need to be risky or expensive’, one of the key enablers to nuclear cost reduction being ‘the intentional commitment to programmes of capacity rather than individual unconnected projects’. 

Additionally, it says, Small Modular Reactor (SMR) and advanced Generation IV reactor deployment costs may fall ‘even lower than those potentially achievable with large contemporary reactor designs to be deployed in countries with developed economies where wage rates for construction labour and project related professional services are relatively high’. 

 That may be optimistic. What if cost do not fall? The report says that ‘in the absence of credible plans to realise nuclear cost reduction, a UK net zero energy system without nuclear is possible, but targeting such a system is risky (unlikely to get to Net Zero) and potentially expensive. Such a non-nuclear scenario might require significant bioenergy and land use change, as well as a vast quantity of renewable energy’. 

The ESC UK Nuclear route 

 In its report, which is based on work started by the the ETI, the now defunct Energy Technologies Institute, ESC looks to ‘an initial optimised programme of around 10 GWe of new Gen III+ capacity beyond HPC [Hinkley Point C] is a decision of low or no regret provided construction duration and costs continue to reduce as predicted by the findings of the ETI Nuclear Cost Drivers project.’ 

What would it all be used for? Balancing? ESC says ‘it is well established that for a balanced, resilient and cost- efficient system, intermittent renewables should be complemented by additional technologies providing firm and mid-merit generation. With the levels of overnight capital cost explained in this report, and used as the basis for the energy system modelling, nuclear technologies have important potential roles to complement energy from wind in providing electricity generation’. That’s hard to take: they are more likely to conflict and lead to curtailment: inflexible nuclear is not much use for balancing variable renewables. 

A bit more credibly, ESC look to nuclear CHP (Combined Heat and Power) feeding district heating networks (DH): ‘All reactor types are capable of cogeneration deployment to supply the lower grade heat required; light-water nuclear SMRs are a good match for thermal energy demand and can be deployed closer to the centre of demand meaning shorter connecting pipes and lower costs for many potential DH locations’. But would local residents be happy having SMRs in or near cities? 

Maybe hydrogen gas generation would be a better bet- it can be piped more easily to where its needed. ESC says ‘advanced nuclear plants coupled with higher temperature more efficient hydrogen production technology can be a cost-effective source of additional hydrogen with low carbon footprint and relatively low land-take’. It sees this possibly offering more flexible operation and possibly cheaper hydrogen than from steam reformation of gas or electrolysis using renewable electricity. Well, that has yet to be proved! And it assumes that new nuclear will be cheaper- a long shot. Whereas renewables are clearly getting cheaper. 

ESC nonetheless is keen to fight it out. It wants to see a UK ‘commitment to a programme of capacity rather than individual unconnected projects, and the benefits from deployment of multiple units in an uninterrupted construction sequence on the same site’. It says ‘this additional capacity can be expected to potentially commence operations between 2028 and 2035 if suitable projects are committed at the right time,’ subject to continuing assessment. And then more later- maybe up to 50 GW by 2050. 
  
NIA also push for 50GW 

That may sound massive, but in a parallel report, the UK Nuclear Industry Association backs the same idea. It says that nuclear power could supply up to 40% of UK power by 2050 from about 32 GW of capacity, including a contribution from fusion, with a further 18 GW of capacity focused on the production of hydrogen and district heating. So 50GW in all. It certainly tries to push all the buttons. As well as supplying direct power, storable hydrogen and heat, the NIA says there’s ‘significant potential to site electricity storage projects near nuclear sites. The UK has a strong history in co-locating such sites, such as the Dinorwig pumped hydro storage plant in Snowdonia near Trawsfynydd nuclear power plant. As newer, innovative storage technologies develop, such as cryogenic liquid, ammonia, and molten salts; nuclear power stations, where grid connectivity is already in place, make ideal locations’. 

That is pushing it a bit. The beauty of these new storage options is that they can be sited anywhere on the grid- they do not need to be near power plants, though that is one option. And at whatever point they are made in the grid system, renewables inputs are likely to be much cheaper. Certainly renewables are winning so far. As IRENA have reported, solar photovoltaics (PV) shows the sharpest cost decline over 2010-2019 at 82%, followed by concentrating solar power (CSP) at 47%, onshore wind at 40% and offshore wind at 29%. The NIA seems to think nuclear can catch up, but a critical commentary in the FT noted that the report ‘contains a barrage of demands including that development costs be paid for, an assured flow of orders and all risks covered by taxpayers or consumers. For an industry in global decline, beset by technical difficulties, overruns and overspends, this is audacious indeed’.  

It is possible that new nuclear technology will get cheaper, and some proponents have come up with very optimistic projections for low cost SMRs, with there being some industrial and political interest in the UK, US, China and elsewhere. But it will take time to find out if it will be possible to deploy large numbers of SMRs to get unit costs down. In at least some critics view, progress so far does not look too encouraging. It seems far more likely that renewable will continue to develop. IRENA says that continuing cost declines confirm renewable power as a low-cost climate and decarbonisation solution, aligning short-term economic needs with medium- and long-term sustainable development goals. Renewable power installations could also form a key component of economic stimulus packages in the wake of the COVID-19 pandemic. IRENA says an annual energy spending of $4.5 trillion could boost world’s economy by 1.3% and create up to 19 million jobs by 2030. There are still those who look to nuclear globally- and even to new EPRs in the UK. However, all in all, renewables, along with energy saving, look like a safer, cleaner, cheaper and faster to deploy option than nuclear.

Comments

  1. "...some proponents have come up with very optimistic projections for low cost SMRs..."

    I was that proponent, Readers! But it wasn't me 'making it up'. Down the RH pane of this Blogspot is all the links you'll need to find out about the progress of GE Hitachi's BWRX-300 SMR.

    GE Hitachi have been in the [nuclear power] game since the 50s and threw the breakers on their 50th BWR Nuclear Power Plant (NPP) in the 80s. It is they who are openly proclaiming on their BWRX-300 webpage, a capital cost of $2,250/kW.

    The capital cost for 3,200 MW, like Sizewell C, would be £5.6 billion - that's 72% below the £20 billion price tag for Sizewell's 2 EPRs - and it's easy to see why, if you have a bit of engineering nous.

    And the BWRX-300 has a 2 years build programme. At last, a NPP that levels the playing field with Wind And Solar Plants (WASPs), in terms of attracting fund managers with those £billions of 'green investments' looking for a home.

    Every £1.00 invested in a BWRX-300 will 'earn' 7.2X more than £1.00 invested in onshore wind; 12X more than offshore wind; 17.5X more than utility scale solar. And the 'product' is so superior - it's the 24/7/365 version of electricity and completely free of the 'Intermittency Problem' that will just not go away for WASPs.

    There's a facebook Group for the BWRX-300 too - heading for 500 Members and building up a real head of steam. Get on the bandwagon now!

    ReplyDelete

Post a Comment

Popular posts from this blog

Global Energy Outlooks - BP v Jacobson

The share of renewables in global primary energy may increase ‘from around 10% in 2019 to between 35-65% by 2050, driven by the improved cost competitiveness of renewables, together with the increasing prevalence of policies encouraging a shift to low-carbon energy’. So says BP in its latest Global Energy Outlook . It does see wind and solar accounting ‘for all or most of the growth in power generation’, but even at the top of the range quoted, it still falls a lot short of the renewable ‘100% of total energy’ scenarios that have been produced by some academics in recent years.  To fill the gap to zero net carbon, BP sees wide-scale use being made use of carbon capture technology, as well as some nuclear power. And it says ‘Natural declines in existing production sources mean there needs to be continuing upstream investment in oil and natural gas over the next 30 years’. You won’t find much support for these fossil and nuclear options in the scenarios produced by Stanford Universi...

Renewables beat nuclear - even with full balancing included

A new Danish study comparing nuclear and renewable energy systems (RES) concludes that, although nuclear systems require less flexibility capacity than renewable-only systems, a renewable energy system is cheaper than a nuclear based system, even with full backup: it says ‘lower flexibility costs do not offset the high investment costs in nuclear energy’.  It’s based on a zero-carbon 2045 smart energy scenario for Denmark, although it says its conclusions are valid elsewhere given suitable adjustments for local conditions. ‘The high investment costs in nuclear power alongside cost for fuel and operation and maintenance more than tip the scale in favour of the Only Renewables scenario. The costs of investing in and operating the nuclear power plants are simply too high compared to Only Renewables scenario, even though more investment must be put into flexibility measures in the latter’.  In the Danish case, it says that ‘the scenario with high nuclear implementation is 1.2 bil...

The IEA set out a way ahead

The International Energy Agency's new Global Energy Roadmap sets a pathway to net zero carbon by 2050, with, by 2040, the global electricity sector reaching net-zero emissions. It wants no investment in new fossil fuel supply projects, and no further final investment decisions for new unabated coal plants. And by 2035, it calls for no sales of new internal combustion engine passenger cars. Instead it looks to ‘the immediate and massive deployment of all available clean and efficient energy technologies, combined with a major global push to accelerate innovation’.  The pathway calls for annual additions of solar PV to reach 630 GW by 2030, and those of wind power to reach 390 GW. All in, this is four times the record level set in 2020. By 2050 it wants about 24,000 GW of wind and solar to be in place. A major push to increase energy efficiency is also seen as essential, with the global rate of energy efficiency improvements averaging 4% a year through 2030, about three times the av...